SSC CGL Time and Work Questions

19 questions on Time and Work for SSC CGL, including questions from 2024 papers. Each comes with the correct answer and a worked explanation.

Questions
19
Moderate
19

Time and Work questions with solutions

Q1.Time and WorkModerate

Riya can complete a piece of work in 12 days and Neha can complete the same work in 24 days. In how many days will they finish it working together?

  1. (A)7 days
  2. (B)10 days
  3. (C)12 days
  4. (D)8 days
Show answer and explanation

Correct answer: (D) 8 days

Riya's one-day work = 1/12 and Neha's one-day work = 1/24. Together they do 1/12 + 1/24 = 36/288 = 1/8 of the work per day, so the work is finished in 8 days.

Shortcut: Days together = (a × b)/(a + b) = 288/36 = 8.

Open question page

Q2.Time and WorkModerate

Manoj can complete a piece of work in 6 days and Divya can complete the same work in 12 days. In how many days will they finish it working together?

  1. (A)3 days
  2. (B)6 days
  3. (C)9 days
  4. (D)4 days
Show answer and explanation

Correct answer: (D) 4 days

Manoj's one-day work = 1/6 and Divya's one-day work = 1/12. Together they do 1/6 + 1/12 = 18/72 = 1/4 of the work per day, so the work is finished in 4 days.

Shortcut: Days together = (a × b)/(a + b) = 72/18 = 4.

Open question page

Q3.Time and WorkModerate

Karan can complete a piece of work in 12 days and Neha can complete the same work in 36 days. In how many days will they finish it working together?

  1. (A)8 days
  2. (B)11 days
  3. (C)24 days
  4. (D)9 days
Show answer and explanation

Correct answer: (D) 9 days

Karan's one-day work = 1/12 and Neha's one-day work = 1/36. Together they do 1/12 + 1/36 = 48/432 = 1/9 of the work per day, so the work is finished in 9 days.

Shortcut: Days together = (a × b)/(a + b) = 432/48 = 9.

Open question page

Q4.Time and WorkModerate

Sneha can complete a piece of work in 20 days and Vikram can complete the same work in 80 days. In how many days will they finish it working together?

  1. (A)16 days
  2. (B)50 days
  3. (C)15 days
  4. (D)18 days
Show answer and explanation

Correct answer: (A) 16 days

Sneha's one-day work = 1/20 and Vikram's one-day work = 1/80. Together they do 1/20 + 1/80 = 100/1600 = 1/16 of the work per day, so the work is finished in 16 days.

Shortcut: Days together = (a × b)/(a + b) = 1600/100 = 16.

Open question page

Q5.Time and WorkModerate

Anita can complete a piece of work in 15 days and Amit can complete the same work in 60 days. In how many days will they finish it working together?

  1. (A)45 days
  2. (B)14 days
  3. (C)11 days
  4. (D)12 days
Show answer and explanation

Correct answer: (D) 12 days

Anita's one-day work = 1/15 and Amit's one-day work = 1/60. Together they do 1/15 + 1/60 = 75/900 = 1/12 of the work per day, so the work is finished in 12 days.

Shortcut: Days together = (a × b)/(a + b) = 900/75 = 12.

Open question page

Q6.Time and WorkModerateSSC CGL 2024

Suresh can complete a piece of work in 24 days and Manoj can complete the same work in 40 days. In how many days will they finish it working together?

  1. (A)16 days
  2. (B)15 days
  3. (C)32 days
  4. (D)17 days
Show answer and explanation

Correct answer: (B) 15 days

Suresh's one-day work = 1/24 and Manoj's one-day work = 1/40. Together they do 1/24 + 1/40 = 64/960 = 1/15 of the work per day, so the work is finished in 15 days.

Shortcut: Days together = (a × b)/(a + b) = 960/64 = 15.

Open question page

Q7.Time and WorkModerateSSC CGL 2024

Amit can complete a piece of work in 6 days and Karan can complete the same work in 12 days. In how many days will they finish it working together?

  1. (A)6 days
  2. (B)4 days
  3. (C)3 days
  4. (D)9 days
Show answer and explanation

Correct answer: (B) 4 days

Amit's one-day work = 1/6 and Karan's one-day work = 1/12. Together they do 1/6 + 1/12 = 18/72 = 1/4 of the work per day, so the work is finished in 4 days.

Shortcut: Days together = (a × b)/(a + b) = 72/18 = 4.

Open question page

Q8.Time and WorkModerateSSC CGL 2024

Karan can complete a piece of work in 30 days and Suresh can complete the same work in 60 days. In how many days will they finish it working together?

  1. (A)19 days
  2. (B)20 days
  3. (C)22 days
  4. (D)30 days
Show answer and explanation

Correct answer: (B) 20 days

Karan's one-day work = 1/30 and Suresh's one-day work = 1/60. Together they do 1/30 + 1/60 = 90/1800 = 1/20 of the work per day, so the work is finished in 20 days.

Shortcut: Days together = (a × b)/(a + b) = 1800/90 = 20.

Open question page

Q9.Time and WorkModerateSSC CGL 2024

Divya can complete a piece of work in 18 days and Vikram can complete the same work in 36 days. In how many days will they finish it working together?

  1. (A)12 days
  2. (B)14 days
  3. (C)27 days
  4. (D)18 days
Show answer and explanation

Correct answer: (A) 12 days

Divya's one-day work = 1/18 and Vikram's one-day work = 1/36. Together they do 1/18 + 1/36 = 54/648 = 1/12 of the work per day, so the work is finished in 12 days.

Shortcut: Days together = (a × b)/(a + b) = 648/54 = 12.

Open question page

Q10.Time and WorkModerateSSC CGL 2024

Riya can complete a piece of work in 14 days and Rahul can complete the same work in 35 days. In how many days will they finish it working together?

  1. (A)21 days
  2. (B)12 days
  3. (C)24.5 days
  4. (D)10 days
Show answer and explanation

Correct answer: (D) 10 days

Riya's one-day work = 1/14 and Rahul's one-day work = 1/35. Together they do 1/14 + 1/35 = 49/490 = 1/10 of the work per day, so the work is finished in 10 days.

Shortcut: Days together = (a × b)/(a + b) = 490/49 = 10.

Open question page

Q11.Time and WorkModerateSSC CGL 2024

Rahul can complete a piece of work in 15 days and Amit can complete the same work in 30 days. In how many days will they finish it working together?

  1. (A)12 days
  2. (B)10 days
  3. (C)15 days
  4. (D)9 days
Show answer and explanation

Correct answer: (B) 10 days

Rahul's one-day work = 1/15 and Amit's one-day work = 1/30. Together they do 1/15 + 1/30 = 45/450 = 1/10 of the work per day, so the work is finished in 10 days.

Shortcut: Days together = (a × b)/(a + b) = 450/45 = 10.

Open question page

Q12.Time and WorkModerateSSC CGL 2024

Riya can complete a piece of work in 20 days and Karan can complete the same work in 80 days. In how many days will they finish it working together?

  1. (A)50 days
  2. (B)18 days
  3. (C)15 days
  4. (D)16 days
Show answer and explanation

Correct answer: (D) 16 days

Riya's one-day work = 1/20 and Karan's one-day work = 1/80. Together they do 1/20 + 1/80 = 100/1600 = 1/16 of the work per day, so the work is finished in 16 days.

Shortcut: Days together = (a × b)/(a + b) = 1600/100 = 16.

Open question page

Q13.Time and WorkModerateSSC CGL 2024

Neha can complete a piece of work in 24 days and Riya can complete the same work in 40 days. In how many days will they finish it working together?

  1. (A)32 days
  2. (B)14 days
  3. (C)17 days
  4. (D)15 days
Show answer and explanation

Correct answer: (D) 15 days

Neha's one-day work = 1/24 and Riya's one-day work = 1/40. Together they do 1/24 + 1/40 = 64/960 = 1/15 of the work per day, so the work is finished in 15 days.

Shortcut: Days together = (a × b)/(a + b) = 960/64 = 15.

Open question page

Q14.Time and WorkModerateSSC CGL 2024

Karan can complete a piece of work in 45 days and Vikram can complete the same work in 90 days. In how many days will they finish it working together?

  1. (A)45 days
  2. (B)67.5 days
  3. (C)32 days
  4. (D)30 days
Show answer and explanation

Correct answer: (D) 30 days

Karan's one-day work = 1/45 and Vikram's one-day work = 1/90. Together they do 1/45 + 1/90 = 135/4050 = 1/30 of the work per day, so the work is finished in 30 days.

Shortcut: Days together = (a × b)/(a + b) = 4050/135 = 30.

Open question page

Q15.Time and WorkModerateSSC CGL 2024

Divya can complete a piece of work in 36 days and Sneha can complete the same work in 45 days. In how many days will they finish it working together?

  1. (A)22 days
  2. (B)40.5 days
  3. (C)20 days
  4. (D)9 days
Show answer and explanation

Correct answer: (C) 20 days

Divya's one-day work = 1/36 and Sneha's one-day work = 1/45. Together they do 1/36 + 1/45 = 81/1620 = 1/20 of the work per day, so the work is finished in 20 days.

Shortcut: Days together = (a × b)/(a + b) = 1620/81 = 20.

Open question page

Showing 15 of 19 questions. Start a practice set above to work through the rest.

Frequently asked questions

How many SSC CGL Time and Work questions can I practise here?

19 questions — 19 moderate. 15 are shown on this page with answers and explanations, and the practice set draws from all of them.

How should I practise Time and Work for SSC CGL?

Read through a few solved questions first to see the method, then take a timed practice set. Afterwards, check which questions you got wrong or spent longest on and redo those before moving on.