SSC CHSL Time and Work question with solution

Time and WorkModerate

Sneha can complete a piece of work in 14 days and Amit can complete the same work in 35 days. In how many days will they finish it working together?

  1. (A)9 days
  2. (B)21 days
  3. (C)10 days
  4. (D)24.5 days

Correct answer: (C) 10 days

Sneha's one-day work = 1/14 and Amit's one-day work = 1/35. Together they do 1/14 + 1/35 = 49/490 = 1/10 of the work per day, so the work is finished in 10 days.

Shortcut: Days together = (a × b)/(a + b) = 490/49 = 10.