Rahul can complete a piece of work in 6 days and Suresh can complete the same work in 12 days. In how many days will they finish it working together?
- (A)3 days
- (B)4 days
- (C)9 days
- (D)6 days
Correct answer: (B) 4 days
Rahul's one-day work = 1/6 and Suresh's one-day work = 1/12. Together they do 1/6 + 1/12 = 18/72 = 1/4 of the work per day, so the work is finished in 4 days.
Shortcut: Days together = (a × b)/(a + b) = 72/18 = 4.
About this question
- Subject
- Quantitative Aptitude
- Topic
- Time and Work
- Exam
- SSC GD
- Attempts on SSC Rank
- Not attempted yet
More SSC GD Time and Work questions
- Sneha can complete a piece of work in 14 days and Amit can complete the same work in 35 days. In how many days will they finish it working…
- Pooja can complete a piece of work in 6 days and Karan can complete the same work in 12 days. In how many days will they finish it working…
- Anita can complete a piece of work in 15 days and Amit can complete the same work in 60 days. In how many days will they finish it working…
- Sneha can complete a piece of work in 20 days and Vikram can complete the same work in 80 days. In how many days will they finish it workin…
- Karan can complete a piece of work in 12 days and Neha can complete the same work in 36 days. In how many days will they finish it working…
- Manoj can complete a piece of work in 6 days and Divya can complete the same work in 12 days. In how many days will they finish it working…
Last reviewed on 5 Oct 2026. Spotted a mistake? See our correction policy.