Skip to main content
SSC Rank

SSC MTS Time and Work question with solution

Time and WorkModerateSSC MTS 2024

Sneha can complete a piece of work in 10 days and Riya can complete the same work in 15 days. In how many days will they finish it working together?

  1. (A)8 days
  2. (B)5 days
  3. (C)12.5 days
  4. (D)6 days

Correct answer: (D) 6 days

Sneha's one-day work = 1/10 and Riya's one-day work = 1/15. Together they do 1/10 + 1/15 = 25/150 = 1/6 of the work per day, so the work is finished in 6 days.

Shortcut: Days together = (a × b)/(a + b) = 150/25 = 6.

About this question

Subject
Quantitative Aptitude
Topic
Time and Work
Exam
SSC MTS 2024
Attempts on SSC Rank
Not attempted yet

Appears in: SSC MTS 2024 Computer Based Examination Question Paper — 30 September, Shift 1

More SSC MTS Time and Work questions

Last reviewed on 5 Oct 2026. Spotted a mistake? See our correction policy.