SSC CHSL Time and Work question with solution

Time and WorkModerateSSC CHSL 2024

Anita can complete a piece of work in 10 days and Pooja can complete the same work in 40 days. In how many days will they finish it working together?

  1. (A)30 days
  2. (B)7 days
  3. (C)25 days
  4. (D)8 days

Correct answer: (D) 8 days

Anita's one-day work = 1/10 and Pooja's one-day work = 1/40. Together they do 1/10 + 1/40 = 50/400 = 1/8 of the work per day, so the work is finished in 8 days.

Shortcut: Days together = (a × b)/(a + b) = 400/50 = 8.